A password will be e-mailed to you.

In the early 1900s, the New Milford Power Company successfully completed the first commercially viable hydroelectric power plant on the Housatonic River in Connecticut. The project, Bulls Bridge Development, broke ground in spring 1902 and was in operation by 1903. Bulls Bridge was named after the Bull family, who had lived in the area for generations.

The Bulls Bridge Power Plant, now owned by FirstLight Power Resources, is part of its five-station hydroelectric operation along the Housatonic River, which includes the Falls Village plant in Canaan, the Rocky River plant in New Milford, the Shepaug plant in Southbury, and the Stevenson plant in Monroe.

The Bulls Bridge Power Plant generates as much as 8.4 megawatts as a run-of-the-river hydroelectric facility with a discharge capacity of 1,250 cubic feet per second. This run-of-the-river facility diverts a portion of the river flow upstream of the main dam into a 2.5-mile-long power canal leading to the forebay gatehouse and the recently replaced penstocks. The original, 420-foot-long, 13-foot- and 8-foot-diameter steel penstocks dropped 98 feet from the forebay to the powerhouse. The plant still generates power with the six original horizontal, double-runner, Francis turbines.

Fill material was placed approximately 2 feet above the pipe centerline,
leaving 3 feet exposed.

Each year since 2013, the aging Bulls Bridge penstock had to be dewatered, inspected, and repaired as necessary. The penstocks were exhibiting deformation and corrosion at the saddle supports. In 2013 and 2014, numerous metal plate patches and weld repairs were required to mend leaks on the 13-foot- and 8-foot-diameter penstocks, but reliability concerns led to a need for rehabilitation or replacement of the 100-year-old penstocks.

Gomez and Sullivan Engineers of Utica, N.Y., evaluated alternatives for replacement or rehabilitation of the steel penstocks. Four alternative solutions were developed and evaluated:

  • replace the existing 13-foot-diameter penstocks in-kind;
  • replace both penstocks with a single, 14-foot by 14-foot cast-in-place concrete box type penstock or a single 15-foot-diameter steel penstock;
  • replace both penstocks with two, 10-foot-diameter fiberglass-reinforced (FRP) penstocks; or
  • rehabilitate the existing penstocks and foundations.

Evaluations focused on four possible replacement materials: steel, concrete, HDPE, and fiberglass.

“The alternatives analysis report provided to FirstLight by Gomez and Sullivan recommended either an in-kind replacement of the existing steel pipe or replacement with new fiberglass pipe,” said Ben Sawyer, civil/structural engineer, Gomez and Sullivan. “FirstLight selected the fiberglass replacement alternative because that alternative was the most cost effective option that still provided a similar amount of net generation compared to the existing configuration. FirstLight had also previously used Hobas pipe at the nearby Rocky River Project and had a good experience using Hobas pipe at that site.”

The penstocks were replaced between September 2015 and January 2016 with 10-foot-diameter centrifugally cast, fiberglass-reinforced, polymer mortar (CCFRPM) pipe. Hobas Pipe USA manufactured 600 feet of 10-foot (120-inch) CCFRPM pipe for this replacement project.

Bancroft Contracting, Corp. designed an onsite transportation device used to install the pipe under the bridge.

After FirstLight selected FRP, it had to choose between Hobas and another option. FirstLight’s experience with Hobas on the Rocky River Penstock had much to do with it. The selection criteria included quality control/quality assurance program, product uniformity, coupling sealing surface, assembly technique, joint testing, interior and exterior smooth finish, domestic manufacturing facility, proven at large diameters and wall thickness, and engineering technical assistance.

Installation posed its own challenges. The steep job site was located in a remote area with a section under an existing highway bridge with low overhead clearance. It was also necessary to construct a temporary road and crane pad to access the penstock replacement area from midway along its route from the forebay to the powerhouse.

Bancroft Contracting Corp. of South Paris, Maine, the installation contractor, designed an onsite transportation device to install the pipe under the bridge.

“The rig involved a long I-beam connected to a column,” Sawyer said. “The column was composed of two hollow steel square tubes with one sliding inside the other and held in place with steel pins. Wheels were attached to the bottom of the column. The end of the beam not connected to the column was attached to the arm of an excavator which could then drive the rig through a section of pipe and extend the column to lift the pipe off the ground. Then the rig was driven up to an installed section of pipe and the column could be lowered to drive the rig into the installed pipe and butt the new section of pipe against the installed section.”

The new penstocks were partially buried 2 feet above the spring line, utilizing no cradles for support to optimize installation cost. The fill material was placed to about 2 feet above the pipe centerline, leaving 3 feet exposed. The CCFRPM pipe was designed and manufactured with an operating pressure of 50 pounds per square inch to accommodate the operating pressure of the line. The penstock was put into service during January 2016.


Erin Boudreaux is marketing manager for Hobas Pipe USA (www.hobas.com). Stuart Piermarini is engineering and compliance manager with FirstLight Power Resources (www.h2opower.com/firstlight-power), which specializes in hydroelectric power generation in Ontario, Canada and the Northeastern U.S.

X